Companies working on the ELT
Company |
Service |
Logo |
Start date |
Planned end date |
Design and construction of the Paranal ELT Technical Facility |
|
Mar-18 |
Jul-19 |
|
Dome and telescope structure design and construction contract |
May-16 |
May-23 |
||
M4 mirror phase 1 preliminary design |
|
May-12 |
Jan-15 (completed) |
|
M4 mirror unit final design and manufacturing |
|
Jun-15 |
Jan-23 |
|
Design and manufacturing of M1 mirror coating plants |
|
Jun-18 |
Nov-21 |
|
M1 mirror segment supports design and qualification units |
|
Feb-15 |
Oct-17 (completed) |
|
Core integration infrastructure |
|
Jul-17 |
Jun-20 |
|
ISVV consultancy services |
|
Jan-16 |
Dec-19 |
|
Dataflow Software Components for ELT |
|
Nov-18 |
Nov-22 |
|
FAMES (FOGAL, Micro-Epsilon) |
M1 mirror edge sensors design and manufacturing |
|
Jan-17 |
May-22 |
C-RED cameras for the MAORY instrument |
|
Jul-18 |
Sep-20 |
|
Road and platform construction |
|
Dec-13 |
Feb-17 (completed) |
|
PFS-A main system design and manufacturing |
|
Apr-18 |
Feb-24 |
|
MAORY instrument construction |
|
Feb-16 |
Aug-25 |
|
PA consultancy services |
|
Jan-16 |
Dec-19 |
|
MICADO instrument construction |
|
Oct-15 |
Mar-25 |
|
METIS instrument construction |
|
Oct-15 |
Mar-26 |
|
M1 mirror position actuators |
|
Jun-17 |
Sep-22 |
|
Consultancy support |
|
Jun-13 |
May-21 |
|
Electrical power supply 2017 — |
|
|
|
|
M4 mirror shells supply |
|
Jul-15 |
Nov-23 |
|
M2 mirror and auxiliary equipment supply |
|
Jul-16 |
Feb-24 |
|
M3 mirror and auxiliary equipment supply |
|
Feb-17 |
Sep-23 |
|
M1 mirrors polishing |
|
May-17 |
Jun-23 |
|
M5 mirror blank and polishing |
|
Mar-19 |
Sep-24 |
|
M2 mirror blank supply |
|
Jan-17 |
Jan-19 (completed) |
|
M3 mirror blank supply |
|
Jan-17 |
Jul-19 |
|
M1 mirror blanks supply |
|
May-17 |
Sep-22 |
|
Construction all risks insurance |
|
Mar-18 |
Mar-26 |
|
M2 and M3 mirror cell design and manufacturing |
|
Jan-17 |
Jul-22 |
|
Supply, and installation of ABC power substations (23kV + 0.4 kV) |
|
Oct-16 |
Jul-17 (completed) |
|
HARMONI instrument construction |
|
Oct-15 |
Apr-26 |
|
Infrared detectors for the HARMONI, MICADO, METIS instruments |
|
Jul-18 |
Jan-23 |
|
Laser sources |
|
Dec-17 |
Dec-22 |
|
M1 mirror segment supports design and qualification units |
|
Jan-15 |
Jul-17 (completed) |
|
M1 mirror segment supports series production |
|
Apr-18 |
May-22 |