SciOp

EUROPEAN SOUTHERN OBSERVATORY

La Silla Observatory

SCIENCE OPERATION DEPARTMENT


SciOp


3.6m Telescope M2 Upgrade:
Minutes of the Final Design Review Meeting

LSO-MIN-ESO-90000-0003/1.0

Prepared Olivier Hainaut 2003-06-04
Reviewed Gerardo Ihle 2003-06-10
Released Olivier Hainaut 2003-06-11

Revision History

0.1
2003-06-04 first draft, ohainaut
1.0 2003-06-11 release after review, ohainaut

Content


1.- INTRODUCTION

1.1- PURPOSE & SCOPE

This document contains the minutes of the 3.6m telescope f/8 M2 project Final Design Review (2003-06-03).

More than a formal FDR, this meeting was a progress report of the project, as many items are already completed or well into construction phase. This document also makes references to the "Delta Review" that took place on 2003-05-06.

1.2- STYLISTIC CONVENTION

-

1.3- ACRONYMS AND DEFINITIONS

SciOp: La Silla Science Operation Department
LED: La Silla Engineering Department


1.4- DOCUMENTS AND REFERENCES

2.-MINUTES

2.1- ATTENDANCE

The meeting took place at LSO and Vitacura on 2003-06-03, 08:30 till 10:30. It was attended by G.Andreoni, I.Kastinen, J.Alonso, W.Eckert, R.Parra, O.Lavin, N.Goncalvez at La Silla, and F.Franza, G.Ihle (Chair), G.LoCurto, A.Gilliotte and O.Hainaut in Vitacura.

2.2- MECHANICS

G.Ihle reported on the mechanical design of the upgraded M2 unit, and on the advancement of the work. This was done in detail to the benefit of F.Franza, guest from ESO/HQ and specialist in opto-mechanic design.

Focus Unit:

XY table:

Pantograph:

Spider:

Inner body:

Construction under way - there were some delays caused by other projects interfering. GAn will take care of assigning priorities in order not to cause unacceptable delays.

Outer Body:

The outer body is designed with some stiffening rims, that can take the load of the current full preload of the spider while remaining within specs.

Cooling of the top control unit:

M2 Baffle:

This upgrade will re-install the current M2 baffle. A secondary project will take care of replacing it with an advanced baffle with air circulation (like NTT). Indeed, the improvement of the 3p6m Image Quality is likely to make the aberrations caused by the current baffle significant (while they are currently lost in the noise of the other sources).

2.3- CONTROL ELECTRONICS

Note: The presentation of the control electronic by JAl at this meeting was very short, essentially addressing the points that remained pending after the 2003-05-06 meeting. This section includes part of the discussion that took place at that previous meeting.

The control electronics is designed as fully VLT compliant, in a thermally neutral enclosure. It consists in a harmonic motor - encoder units, forming with the controller a closed velocity loop. The system includes precision limit switch, backed up by heavy duty safety limit switches.

As mentioned before, the total dissipation is about 500W, requiring a cooling system using cooling water. This, in turns, has some constraints on the mechanical design (see above), and implies that the water temperature must be controlled and adjusted wrt the dew point.

At the time of the previous meeting, the CPU, Maccon and amplifiers had not been purchased yet. This has been done by the time of this meeting.

The motors had originally been purchased equipped with brakes. However, the presence of these brakes does not make sense in the closed loop design used, therefore the motors had to be returned to the manufactor for removal. This has been done. GIh will track the motors and make sure they are not stalled in some remote storage.

2.4- SIMULATIONS

At the previous meeting, NGo presented detailed simulations of the full control system, in order to study the precision achieved in positioning the mirror. Indeed, as the position of the motors (as opposed to that of the M2) is measured, this is critical. It appears from these simulations that damping of the system is critical in order for M2 to reach its position in reasonible time and not to oscillate around that position.

2.5- VARIAE and SUMMARY OF ACTIONS

Actions listed earlier:

 

--oOo--